Sunday, October 13, 2024
HomeRegional NewsBoeing Upfitting Interior of North Charleston 787 Final Assembly Factory

Boeing Upfitting Interior of North Charleston 787 Final Assembly Factory

Add another ongoing construction project to the list at Boeing’s 787 plant in North Charleston. According to a county government filing, the plane maker has begun upfitting another 77,000 square feet in its final assembly factory by the airport.

The Post and Courier reports Hitt Contracting submitted the one-page contractor’s notice of project commencement this week. It says the “4th floor fit out” began April 26 but gives no more details.  It’s just the latest upgrade or development at the Boeing complex.

Late last summer, Boeing began expanding both its aft-fuselage factory and its campus paint shop. Shortly thereafter, work began on 30,000 sq. ft. of lab and office space in the final assembly building.

And then, in late January, construction crews began building a DreamlifterOperationsCenter on the back of the mid-body building, adding a staging area for parts ready to be shipped out via the modified 747s.

Meanwhile, Boeing last month announced an agreement to invest another $1 billion and hire 2,000 more people in South Carolina over the next eight years in exchange for $120 million from the state and other tax breaks from the county.

In addition to land, building and job growth, the North Charleston campus is also diversifying beyond 787 work. It’s in the process of bringing on 20 737 workers and many more information technology staff. Read More.

RELATED ARTICLES

Most Popular

Recent Comments