To view this page ensure that Adobe Flash Player version
11.1.0 or greater is installed.
BOSCH REXROTH
The shell building required a new rein-
forced steel floor, new mechanical sys-
tems and a technical mezzanine above the
production floor. “We also installed new
drive-in doors for access, modified the
shipping and receiving areas, added office
space and employee welfare areas, new
parking space, a new truck court for ship-
ping and new concrete pads outside for
equipment,” Green said.
Bolding says part of the project’s suc-
cess resulted from identifying long lead
time items and critical cost elements
ahead of time. “We spent a few months
sorting out what the client wanted to do against the cost
and schedule impact of these items and then worked
closely with production, management, engineers and es-
timators. This allowed us to make decisions early in the
process, in some cases making assumptions when not all
of the answers were available.”
Bolding says this process of ‘putting the cart before the
horse’ could have created complications but worked well
because everyone from the owner to the
vendors took part.
Other members of the team also con-
tributed to the compressed schedule.
SteelFab furnished and installed the new
mezzanine. Project manager Jeff Tucker says
his team had to work closely with the engi-
neer of record to get drawings approved
quickly to facilitate the tight schedule.
Green says the entire project team should
be credited with getting the project done on
time and within the capital budget, despite
outside challenges including rising steel
prices. “By monitoring prices and project
costs, we were able to offset climbing costs we couldn’t
control – like the cost of steel - with decisions about
changes we could.”
Hill Electric Company managed the electrical compo-
nent of the project. Project manager David Wolke says the
challenge of installing so much in such a short time was
simplified because O’Neal had the foresight to order much
of the needed equipment ahead of time.
Consistent, successful project delivery with no surprises!
Our team delivers the consistent value and on time performance customers expect from
a full service mechanical contractor. Let us show YOU the Waldrop difference on your next project.
• HVAC • Piping • Plumbing • Fabrication • Building Automation
• Design • Maintenance • Geothermal • Solar
OFFICE LOCATIONS: SPARTANBURG – GREENVILLE – CLEMSON
waldropinc.com 864-578-7252
8 – October/November 2013 — The South Carolina Construction News