To view this page ensure that Adobe Flash Player version
11.1.0 or greater is installed.
In November Waldrop received
recognition for the project’s successful
delivery with a best-of-class Associ-
ated Builders and Contractors (ABC) of
the Carolinas Eagle Award at the asso-
ciation's Excellence in Construction
awards banquet in Charlotte, North
Carolina. Originally constructed in 1964, the
36,000 sq. ft. student residence in-
cludes living space for 157 students,
along with public spaces and meeting
rooms. The renovation's original scope
of work included the total demolition
and replacement of the mechanical
systems, upgrading electrical support
systems, removing and replacing exist-
ing single pane windows with thermal
pane systems, fire alarm modifications
and replacing the building’s automa-
tion system.
The biggest challenge at the outset:
the project had to be completed during
the university’s 88-day summer break
and none of the work, including the as-
bestos abatement contracted sepa-
rately by the university, could begin
until the students had moved out.
Waldrop won the project through a
competition among pre-qualified con-
tractors and began the unique process
of leading the design-build project as
the prime contractor.
Waldrop executive vice-president
Dennis Pruitt says, while other compa-
nies may shy away from taking on this
level of responsibility, Waldrop uses its
wide breadth of experience and history
of taking on complex projects to em-
brace the challenges.
“We have tremendous depth of con-
struction experience and a strong engi-
neering background within the
company,” he said. “That, coupled with
our design experience qualifies our
team in analyzing projects and gives us
the ability to effectively manage a proj-
ect from concept to a satisfactory end
result.” Pruitt says Waldrop responded to
and won the existing RFP (request for
proposal) but then, in looking at the de-
tails, didn’t believe the design concept
would best serve the university’s over-
all interests relative to cost, maintain-
ability, and energy conservation.
“As the design-build contractor, we
had the ability early on to evaluate the
process and the original design con-
cept,” he said. “From the start we
looked at the design criteria, con-
structability issues and cost impacts
and were able to streamline the
process and improve what had already
been set by the university.”
“The university had an HVAC design
concept but we didn’t think it was the
best application for this project,” he
says. “We went through a process of
helping them understand that the orig-
inal design concept was not the only
option available, gave them additional
options to consider, and helped facili-
tate their decision-making process to-
ward applied systems that better
served their needs.”
The resulting change provided an
The South Carolina Construction News — December 2013 / January 2014 – 3