To view this page ensure that Adobe Flash Player version
11.1.0 or greater is installed.
State of the Art Manufacturing Facility
Created in Existing Warehouse
Heather Seftel-Kirk
South Carolina Construction News
Greenville-based O’Neal, Inc., converted a 10-year-old,
pharmaceutical warehouse in Fountain Inn into a state of
the art manufacturing plant for its client
Bosch Rexroth. Completed in just six
months, and within the project’s
budget of $15 million, the 265, 000 sq.
ft. plant required close collaboration,
with subcontractors working side by
side and typical construction schedules
adjusted to meet the tight demands.
Using engineer-procure-construc-
tion (EPC) project delivery method,
O’Neal’s facility upgrades included new
steel reinforcement for a utility mezza-
nine, electrical upgrades, chilled water lines, heat treating,
compressed air systems, and a new concrete reinforced
slab for machining equipment. The project also included
12,000 square feet of new office space and upgrades to
all utility services.
A technical support mezzanine located over the produc-
tion area, designed to support a utility distribution system,
as well as overhead hoists required for plant operations
and equipment installation, were installed. A state of the
art fire protection system, compliant with Bosch and its in-
surer’s standards, was also required.
Shane Bolding, business unit leader at O’Neal Inc., says
the project had been part of Bosch’s expansion plans for
several years but when the time came for construction, it
had to be implemented very quickly to expand the com-
pany’s manufacturing capacity and customer require-
ments. The project used an existing structure and nearby
available land . “They could have just torn down the old
shell but instead used it to create a state of the art manu-
facturing facility within an existing distribution building,”
Bolding said. “While this created some challenges it also
protected the work from weather related issues because
the structure was already enclosed.”
Bosch North American director
Jerry Greene says among the chal-
lenges facing the team, an already
short, eight month schedule was
compressed to six months and
normal construction schedules
had to be adjusted. “Construction
began in January but we needed
to be in as early as possible to
start installing our own equip-
ment. We got a partial certificate
of occupancy so we started mov-
ing that equipment in by February. O’Neal’s project man-
ager and team were terrific at helping things along and
knowing how best to handle this.”
South Carolina Construction News is distributed throughout
the Carolinas construction industry from offices at
127 College Avenue, Durham, NC 27713.
SCCN is circulated on a controlled circulation list to
qualified readers including members of most
major construction associations in the Carolinas.
For information contact: Bob Kruhm at 919-544-3719
or email rkruhm@nc.rr.com.
ISSN 1940-3682.
The South Carolina Construction News — October/November 2013 – 7