To view this page ensure that Adobe Flash Player version
11.1.0 or greater is installed.
“float” of the concrete. Even having the steel galvanized
to resist environmental corrosion influenced the accuracy
of sizings, said Hutchins.
Such precision then enabled Williams Erection of At-
lanta – whose portfolio includes work on the Bank of Amer-
ica connecting bridge in Charlotte plus numerous sports
arenas, hotels and so on throughout the southeastern U.S.
— to lift and position the steel into place smoothly. It also
required corresponding precision for the concrete.
“It’s not every day a project like the wind turbine site
comes along and when it did we knew we wanted to be a
part of it,” said John DeWitte, president of Cooper River
Concrete in Charleston. “Since this had never been done
before we had no historical data to draw from. Each ele-
ment of the reinforcing (steel) and concrete work had to
be carefully planned, step by step.”
The type of concrete used was important.
“Due to the congestion of multiple layers of #11 rein-
forcing bars we knew that conventional concrete was not
going to work,” DeWitte said. “We had worked on a num-
ber of local projects using self-consolidating concrete and
knew that this was the answer to ensuring that we had
proper consolidation of the concrete. SCC has chemical
viscosity modifiers that hold the matrix of the concrete to-
gether while increasing the slump or spread of the con-
crete to 24” to 28”. The high level of fluidity allows the
concrete to flow throughout the rebar and formwork with-
4 – October/November 2013 — The South Carolina Construction News
out the need of mechanical vibration. During the process
over 4,000 cubic yards of SCC were placed on this proj-
ect.” Specifically, DeWitte, said, the foundation pours for the
7.5 MW and 15 MW were 750 cubic yards and 2,000 cubic
yards respectively. “One concern of placing this mass con-
crete was the control of hydration heat,” he said. “Through
the placement of temperature sensors in the 7.5 MW foun-
dation we were able to monitor the temperature of the
concrete through the curing process.”
Dudas said it took months of preparation for the con-
crete pours, which lasted 12 to 16 hours at a time. It was
very exacting work to place and verify tolerances of the
embedded materials.
“This foundation was so large and needed a lot of rebar,
which made it impossible for us to pump and vibrate the
concrete in a traditional manner….(Self consolidating con-
crete) doesn’t need vibration and consolidates completely
around all of the rebar and embeds,” Dudas said.
“Unlike conventional concrete mix, the self-consolidat-
ing mix pours like pea soup, which allows the concrete to
flow around the re-bar,” said Choate Vice President/Divi-
sion Manager Matthew Brewer.
Use of Building Information Modeling software was key
to Choate’s ability to coordinate with subcontractors such
as Cooper River and SteelFab, which began as a small
handrail fabrication shop in Charlotte and now is a major
supplier of fabricated structural steel. “This project was an
excellent use of BIM to coordinate the massive amounts
of rebar and the large number and types of structural steel
that needed to be placed,” he said. A precision metrologist
was used to verify details, too.